KADAPA ULTRA MEGA SOLAR PARK (1000 MW)

Menu

KADAPA ULTRA MEGA SOLAR PARK (1000 MW)

SECI: 750 MW under VGF Scheme.

For 500 MW (Open) + 150 MW (DCR) NIT issued on 30.06.2016.

For 100 MW (with storage) NIT issued on 21.07.2016.

SECI has to issue NIT for tariff based bidding for selection of solar power developers.

NTPC: 250 MW under Bundling Scheme.

NIT issued on 26.10.2016

Bid Opening Date: 09.12.2016.

Reverse auction conducted on 11.04.2017.

Lowest levellised tariff quoted by the bidders: Rs. 3.15 per kWh.

 

NTPC has signed PSA with APDISCOMs on 11.12.2017. LOI is to be issued to selected SPD by NTPC.