KADAPA ULTRA MEGA SOALR PARK (1000 MW) - STATUS

Land Acquisition Details:

Out of total land of 5927.76 Acres, 5427.63 Acres was already acquired.

 

Infrastructure Activities:

Roads & Drains: Tenders will be called by August 2017. Work will be awarded by September 2017. Expected date of completion by 28.02.2018.

Water Supply System: Tenders will be called by August 2017. Work will be awarded by September 2017. Expected date of completion by 28.02.2018.

Cable Tray Supports:Tending is under process.

 

Boundary Fencing: LOI was issued to M/s. Planet Associates on 02.11.2016. Expected date of completion by 31.08.2017.

 

Internal Transmission System: 4 Nos. of 220/33 kV Pooling substations and connecting line up to 400/220 kV Grid Substation, one pooling substation for each block of 250 MW. NIT to be issued by APTRANSCO by August 2017. Expected date of completion by 30.06.2018.

 

External Transmission System: APTRANSCO has decided to establish 400/220 kV Grid substation. Preparation of Tender documents by APTRANSCO is under progress. NIT likely to be issued by August 2017. Expected date of completion by 31.12.2018.