KADAPA ULTRA MEGA SOALR PARK (1000 MW) - STATUS

Land Acquisition Details:

Out of total land of 5927.76 Acres, 5427.63 Acres was already acquired.

 

Infrastructure Activities:

Roads & Drains: Tenders will be called by February 2018. Work will be awarded by March 2018. Expected date of completion by 31.08.2018.

Water Supply System: Tenders will be called by March 2018. Work will be awarded by April 2018. Expected date of completion by 30.09.2018.

Cable Tray Supports: Preparation of estimates are under progress.

 

Boundary Fencing: LOI was issued to M/s. Planet Associates on 02.11.2016. Expected date of completion by 30.03.2018.

Internal Transmission System:For 250 MW in Phase-I, NIT will be issued after issuing LOI by NTPC to SPD.

For balance 750 MW in Phase-II, NIT will be issued after finalisation of tender by SECI for selection of SPDs.

External Transmission System: To be developed by APTRANSCO (STU). 250 MW in Phase-I will be evacuated through nearby 400/220 kV Grid sub-station of APTRANSCO. After finalisation of tender by SECI for balance 750 MW, APTRANSCO will issue NIT for establishment of 400 kV Grid sub-station.

Expected date of completion by 31.01.2019.

 