Andhra Pradesh Solar Power Corporation Private Limited

(A JV Company of Govt of Andhra Pradesh & Govt of India)

govt-logo

ANANTHAPURAMU ULTRA MEGA SOLAR PARK (1500 MW)

Menu

ANANTHAPURAMU ULTRA MEGA SOLAR PARK (1500 MW)- GALIVEEDU - STATUS

Land Acquisition Details:

Out of total land of 3517.07 Acres, 3456.75 Acres was already acquired.

 

Infrastructure Activities:

Roads & Drains: LOI was issued to M/s. IVRCL Ltd. on 15.11.2017. Expected Date of Completion by 28.02.2018.

Water Supply System: NIT issued on 07.02.2017. Price bid opened on 10.04.2017. LOI was issued on 30.08.2017. Expected Date of Completion: 31.03.2018.

Cable Tray Supports: Work is under progress. Works to be completed on 08.03.2018.

Boundary Fencing: Works were completed.

Internal Transmission System: 3 Nos. of 220/33 kV Pooling Sub-Stations and connecting line up to 400/220 kV Grid Sub-station; pooling substations (250 MW, 100 MW & 50 MW). LOI was issued by APTRANSCO on 28.04.2015 for Pooling substations. Land surveying was completed and levelling is under progress.

Schedule to be commissioned by March/April, 2018.

External Transmission System: 400/220 kV Grid Sub-Station at N.P. Kunta is being developed by PGCIL. LOI issued to M/s. Megha Engineering and Infrastructure Ltd on 13.05.15, Transformer Package to M/s Crompton Greaves Ltd on 24.06.15 and Tower package to M/s K. Ramachandra Rao Transmission & Projects Pvt. Ltd. on 15.06.2015. 400/220 kV Grid Sub-Station was charged as detailed below:

500 MVA 400/220kV ICT-1 – 25.04.2016
500 MVA 400/220kV ICT-2 – 01.07.2016
125 MVA Reactor                 – 01.07.2016
500 MVA 400/220kV ICT-3 – 09.07.2016

Evacuation for balance capacity would be ready by January 2018.

 