ANANTHAPURAMU II ULTRA MEGA SOLAR PARK (500 MW) - STATUS

Land Acquisition Details:

Out of total land of 4229.57 Acres, 4124.84 Acres were already acquired.

 

Infrastructure Activities:

Roads & Drains: LOI was issued to C. Gopal Reddy on 27.03.2017. Expected date of completion by 30.09.2017

Water Supply System: Tenders will be called by August 2017. Work will be awarded by September 2017. Expected date of completion by 28.02.2018.

Cable Tray Supports:Tending is under process.

 

Boundary Fencing: Works were completed.

 

Internal Transmission System: 2 Nos. of 220/33 kV Pooling substations and connecting line up to 400/220 kV Grid Substation, one pooling substation for each block of 250 MW. NIT to be issued by APTRANSCO by August 2017. LOI is likely to be issued by the end of October 2017. Expected date of completion by 31.10.2018.

 

External Transmission System: APTRANSCO has decided to establish 400/220 kV Grid substation. Price Bid was opened on 10.03.2017 and LOI was issued to M/s. Tata Projects Ltd. On 24.05.2017. Expected date of completion by 31.08.2018.