ANANTHAPURAMU II ULTRA MEGA SOLAR PARK (500 MW) - STATUS

Land Acquisition Details:
Out of total land of 4229.57 Acres, 4124.84 Acres were already acquired.

Infrastructure Activities:
Roads & Drains: LOI was issued to C. Gopal Reddy on 27.03.2017. Expected date of completion by 15.02.2018.

Water Supply System: NIT was issued on 30.12.2017 and work will be awarded by Feb 2018. Expected date of completion by 31.07.2018.

Cable Tray Supports: Work is under progress. Works to be completed on 30.03.2018.

Boundary Fencing: Works were completed.

Internal Transmission System: 2 Nos. of 220/33 kV Pooling substations and connecting line up to 400/220 kV Grid Substation, one pooling substation for each block of 250 MW. NIT issued in July, 2017 and Technical bids opened on 28.08.2017. LOI was issued on 30.11.2017. Expected date of completion by 31.08.2018.

External Transmission System: APTRANSCO has decided to establish 400/220 kV Grid substation. NIT was issued on 04.01.2017 and Price Bid was opened on 10.03.2017. LOI was issued on 24.05.2017.

Expected date of completion by 31.08.2018.