ANANTHAPURAMU ULTRA MEGA SOLAR PARK (1500 MW) - STATUS

Land Acquisition Details:

Out of total land of 7181.01 acres, 6692.97 acres was already acquired.

Infrastructure Activities:

Roads & Drains:Works were completed.

Water Supply System:Works were completed.

Cable Tray Supports: Works were completed.

Boundary Fencing:Works were completed.

Internal Transmission System: 4 Nos. of 220/33 kV Pooling Sub-Stations and connecting line up to 400/220 kV Grid Sub-station; one pooling sub-station for each block of 250 MW. LOI was issued by APTRANSCO on 28.04.2015 for Pooling substation-I and on 15.09.2015 for remaining pooling stations to M/s. Amara Raja Power Systems Ltd. 220/33 kV Pooling Sub-Station-I with 80 MVA Power Transformers and connected line was commissioned as detailed below:

 

1st& 2nd80 MVA PTR – 30.04.2016
3rd 80 MVA PTR          – 20.05.2016
4th 80 MVA PTR          – 23.07.2016

For remaining 3 Nos. pooling sub-stations at N.P. Kunta Site, civil & erection works are put on hold till finalisation of Solar Power Developer.

External Transmission System: 400/220 kV Grid Sub-Station at N.P. Kunta is being developed by PGCIL. LOI issued to M/s. Megha Engineering and Infrastructure Ltd on 13.05.2015, Transformer Package to M/s Crompton Greaves Ltd on 24.06.2015 and Tower package to M/s K. Ramachandra Rao Transmission & Projects Pvt. Ltd. on 15.06.2015. 400/220 kV Grid Sub-Station was charged as detailed below:

 

500 MVA 400/220kV ICT-1 – 25.04.2016
500 MVA 400/220kV ICT-2 – 01.07.2016
125 MVA Reactor                 – 01.07.2016
500 MVA 400/220kV ICT-3 – 09.07.2016

Evacuation for balance capacity would be ready by January 2018.

 

Commissioning Details for Phase-I(250 MW) by NTPC:

 

100 MW – 30.04.2016
  50 MW – 30.05.2016
  50 MW – 07.06.2016
  50 MW–10.08.2016